1.             Permanent Wall at Splash Wave Pool

 

mur permanent à la piscine à vagues splash

 

 

COMMITTEE RECOMMENDATION

That Council approve Option 2 - the construction of a permanent wall at the Splash Wave Pool, 2040 Ogilvie Road, as described in this report.

 

 

Recommandation du comi

 

Que le Conseil approuve l’option 2 – la construction d’un mur permanent à la piscine à vagues Splash, 2040 rue Ogilvie, tel que décrit dans le présent rapport.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DOCUMENTATION

 

1.                  Deputy City Manager report dated 26 April 2007 (ACS2007-BTS-RPM-0004).

 


Report to/Rapport au :

 

Community and Protective Services Committee

Comité des services communautaires et de protection

 

and Council / et au Conseil

 

26 April 2007 / le 26 avril 2007

 

Submitted by/Soumis par :

Steve Kanellakos, Deputy City Manager, Community and Protective Services/Directeur municipal adjoint, Services communautaires et de protection

 

Contact Person/Personne ressource : Stephen A. Finnamore, Executive Director

Business Transformation Services / Services de transformation des activités

(613) 580-2424 x 28859, steve.finnamore@ottawa.ca

 

Co-ordinated for/Coordonner pour : Aaron Burry, Director

Parks and Recreation/Directeur, Parcs et loisirs

(613) 580-2424 x 23666, aaron.burry@ottawa.ca

 

Ward 11 – Beacon Hill-Cyrville

Ref N°: ACS2007-BTS-RPM-0004

 

 

SUBJECT:

Permanent Wall at Splash Wave Pool

 

 

OBJET :

mur permanent à la piscine à vagues splash

 

 

REPORT RECOMMENDATION

 

That the Community and Protective Services Committee recommend Council approve Option 2 - the construction of a permanent wall at the Splash Wave Pool, 2040 Ogilvie Road, as described in this report.

 

 

RECOMMANDATION DU RAPPORT

 

Que le Comité des services communautaires et de protection recommande que le Conseil approuve l’option 2 – la construction d’un mur permanent à la piscine à vagues Splash, 2040 rue Ogilvie, tel que décrit dans le présent rapport.

 

 


EXECUTIVE SUMMARY

 

The Real Property Asset Management (RPAM) branch is responsible for the replacement of building and park assets that have reached end of life and manages several capital programs dedicated to life cycle renewal work. As part of its 2005/06 capital program, RPAM established a performance-based contract for the replacement of the floating bulkhead at the Splash Wave Pool located on Ogilvie Road in the east end of the City and entered into contract with a local contractor to undertake the design, manufacture and installation of a new floating bulkhead. Despite repeated efforts to retrofit the new bulkhead, the contractor has not been able to provide a floating bulkhead that meets the performance requirements of the facility and its programming. As a result, the facility has been unable to provide wave swims since September 2006, following the annual maintenance program. Based on the lack of performance of the manufactured unit, the City has terminated the contract with the contractor and legal actions may be forthcoming. In concert with the Parks and Recreation branch, RPAM, as well as other municipal divisions, are recommending a different strategy in response to the requirements of the Splash Wave Pool as outlined in this report.

 

 

RÉSUMÉ

 

La Direction de la gestion des biens immobiliers (GBI) est responsable du remplacement des biens immobiliers et des biens se trouvant dans les parcs qui ont atteint la fin de leur vie utile, de même qu’elle gère plusieurs programmes d’immobilisations liés au renouvellement de biens. Dans le cadre de son programme d’immobilisations de 2005-2006, la Direction de la GBI a établi un contrat fondé sur le rendement pour le remplacement de la cloison flottante de la piscine à vagues Splash, située sur le chemin Ogilvie, dans l’est de la ville, et elle a passé un contrat avec un entrepreneur local pour la conception, la fabrication et l’installation d’une nouvelle cloison flottante. En dépit d’efforts répétés pour adapter la nouvelle cloison, l’entrepreneur n’est pas parvenu à fournir une cloison flottante qui réponde aux critères de rendement de l’installation et de ses programmes. En raison de cette situation, les bains dans les vagues sont suspendus depuis le mois de septembre 2006, soit depuis la fin du programme d’entretien annuel. Comme la cloison fabriquée par l’entrepreneur ne donnait pas le rendement escompté, la Ville a résilié le contrat et un recours judiciaire est possible. De concert avec la Direction des parcs et loisirs, la Direction de la GBI et d’autres divisions de la Ville recommandent, pour répondre aux exigences propres à la piscine à vagues Splash, une stratégie différente, qui est décrite dans le présent rapport.

 

BACKGROUND

 

Design Approach

The Splash Wave Pool was constructed in 1987 and was regarded as one of the first indoor wave pools developed in Canada. The design approach that was used for this pool was, and continues to be, a somewhat unique application based on limited financial resources at the time of construction. The design of the pool allows for wave swims and lane swimming as well as associated aquatic club programs and the full gamut of learn-to-swim lessons to be offered at the facility, albeit not all simultaneously. Appendix 1 provides a base drawing of the facility and the pool tank arrangement.

 

Role of Floating Bulkhead

In order for waves to be properly generated and controlled, it has been necessary to physically separate the wave pool portion of the tank from the lap pool. This physical arrangement ensures that the wave action is consistent and allows for the proper dissipation of the waves at the shallow end of the wave pool, thereby mimicking a beachfront. The physical separation of the wave pool and lap pool has been done using a specially built floating bulkhead that acts principally as a moveable wall.

 

Through a series of air-ballast tanks, the floating bulkhead is raised from its resting perch in the deep end of the wave pool and maneuvered by staff using ropes and grab bars to its locking position at the junction where the lap pool meets the wave pool. Once in position, the waves can be generated. At the end of the wave swim period, the floating bulkhead is returned to its resting position in the deep portion of the wave pool and lane swimming, learn-to-swim lessons, club activities and leisure swims can be offered to the public.

 

Typically, bulkheads are used to separate large, uniform pools, such as the Olympic-sized pool at the Nepean Sportsplex, into different sections, allowing various aquatic activities to be offered simultaneously such as diving lessons in the deep end, advanced swimming lessons in the middle portion and children’s programming in the shallow portion. Static and dynamic loads on this type of bulkhead are consistent and minimal. The floating bulkhead at the Splash Wave Pool is subject to more intense dynamic loads and its design and construction is therefore more intricate. The original bulkhead was twenty (20) years old and in poor condition. RPAM initiated a capital project within its capital life cycle renewal program to replace the original bulkhead with a new piece of equipment.

 

Contract Issues

Recognizing that there are few swimming pool bulkhead firms with the design and manufacturing experience to undertake this technical requirement and in view of the fact that the City and the local industry had no extensive experience with swimming pool bulkheads and fiberglass construction, the City issued a performance-based contract that stipulated only the performance requirements of the bulkhead. The design intent, the durability requirements and the ease of movement and set-up of the new bulkhead were key components of the request for tender (RFT) document. The responsibility to design, manufacture and install the new bulkhead rests entirely with the firms submitting responses to the RFT.

 

Two firms submitted tenders for the replacement of the bulkhead and the contract was awarded to a local firm that teamed with a USA-based manufacturer for the design and manufacture of the new floating bulkhead. Time is of the essence in the contract issued to the contractor, with the bulkhead to be fully commissioned and in service by September 22, 2006. Despite repeated efforts to retrofit the bulkhead’s anchoring system, braces and overall stability, the bulkhead does not perform adequately. Staff is of the opinion that the manufactured product does not meet the performance and safety requirements stated in the RFT document. There have been no wave swims at Splash Wave Pool since September 2006.

 

Other Considerations

The approved 2007 capital life cycle renewal budget has earmarked significant work at Splash Wave Pool. The main heating and dehumidification system will be replaced during a planned two-month shutdown in July and August. A contract has been awarded for the purchase of the dehumidification equipment. Plans are to purchase and install a new ultra-violet treatment system to complement the existing pool system. These major initiatives, coupled with roofing replacement work, will enhance the building’s air and environmental systems and ensure the long-term performance of the facility. Staff wishes to integrate any planned replacement of the bulkhead, or other strategy, within this timeline as much as possible.

 

DISCUSSION

 

Option 1 – Establish Contract for New Bulkhead with Second Proponent

On a without prejudice basis, staff has explored with another contractor and its preferred manufacturer the timing and performance issues with regard to an alternative floating bulkhead. Although the contractor and manufacturer have installed numerous bulkheads, their collective experience has been limited to bulkhead installations in pools without wave action. Although the firms believe that they can produce a floating bulkhead that will meet the performance requirements of the original RFT, the firms candidly admit that the failure of the recent bulkhead requires a more cautious approach.

 

At a recent meeting held at the pool, the proponent confirmed that it would take time to access the required engineering expertise and complete the industrial process to configure, design and manufacture a new floating bulkhead. It is not expected to be in place until late December 2007. The proponent commented that they are not afforded an opportunity to see the old or new bulkhead working in order to fashion the final product. The lack of a functioning bulkhead on-site is a factor that has changed since the issuance of the original Request For Tender and creates additional difficulties with the design effort.

 

The installation of the new bulkhead will necessitate a further closure of the pool for a period of up to three weeks, resulting in program cancellations, reduced leisure swims and club bookings. The Parks & Recreation branch has indicated that this program impact would be a major inconvenience to pool users and would generate more complaints and loss of participation and revenue at the Splash Wave Pool, considering the number of closures that the pool has been subjected to since September 2006. There is significant concern about the absence of wave swims at this facility for the entire year.

 

It is understood that within the remaining service life of Splash Wave Pool that another floating bulkhead will have to be designed and manufactured. The availability of bulkhead manufacturers to respond to that future replacement may become a problem. The labour costs related to the moving and set-up of the bulkhead will be a mainstay of the operating budget as well as the on-going maintenance and repair requirements associated with this type of equipment.

 

The upset costs related to Option 1 are estimated at $ 300,000. After reviewing the contractual terms and other matters pertinent to this project, the second proponent has indicated that the progress payment schedule will have to allow an initial payment equal to 55 percent of the contract value in order to acquire the engineering expertise and materials necessary for the design and fabrication of the floating bulkhead. A further 35 percent progress payment is expected at delivery. The concern about extending payments in advance of a proven technical solution remains. The City would insist on performance security in keeping with the provisions of the original RFT.

 

Option 2 – Construct Permanent Wall

Option 2 involves the construction of a permanent wall to separate the lap pool from the wave tank. This work would be done during this year’s planned shutdown in July and wave swims, along with limited learn-to-swim programs, would be available this September. The permanent wall will permit patrons to transition from the slide and wave pool to the hot tub area and will provide an excellent lifeguard station. The internal labour required to move and secure a floating bulkhead would cease under this option. This option provides the quickest and most reliable solution to the re-instatement of wave swims at Splash Wave Pool.

 

From a different perspective, aquatic club activities, lap swimming and some learn-to-swim programs will have to be suspended at the Splash Wave Pool. The Parks & Recreation branch will attempt to find alternate space for the aquatic clubs and these aquatic services; however, given the limited available hours of pool time, it may not be possible to secure pool time that is convenient. Although there are plans to construct new aquatic facilities in the east end of the City, these facilities are not expected to be in service for another three to four years. Certain measures, such as the introduction of free lane swimming devices or other programming features, could form part of this option and lessen the loss of lap swimming and specialized aquatic training and instruction.

 

The estimated cost of Option 2 is $ 115,000. This option recognizes the City’s lack of capital funding to offset the cost of Option 3. It also recognizes that wave swims represent 65 percent of the revenue stream for this pool and works to have wave swims offered at the earliest opportunity.

 

Option 3 – Modification of Splash Wave Pool

This option calls for the adoption of a new strategy for the Splash Wave Pool. The design concept of an integrated wave pool and lap pool is abandoned and a new concrete wall is erected between both tanks. The 25-metre lap pool is replicated by means of an external addition to the pool of approximately 200 square metres, which is below the threshold for site plan review and approval. A new and separate heating and filtration system serves the ‘new’ lap pool. The existing heating and filtration system is assigned exclusively to the wave pool, resulting in greater water treatment capacity.

 

With this physical separation in place and a replicated lap pool, the Splash Wave Pool can offer uninterrupted wave swims throughout each program day and deliver all other programs simultaneously.

 

Adoption of Option 3 would entail an estimated capital cost of $ 1.7M and there is presently no funding source for this option.  In the absence of confirmed funding, this option cannot be pursued at this time.

 


FINANCIAL IMPLICATIONS

 

Funds in the amount of $115,000 are available within the 2007 Lifecycle Renewal – Buildings capital program within the Real Property Asset Management branch to defray the costs for the construction of the permanent wall as described under Option 2.

 

 

RURAL IMPLICATIONS

 

Although the re-construction of the Splash Wave Pool recommended herein is not a rural affairs issue, it is recognized that the Splash Wave Pool draws its participants from a wide geographical area, including residents from the rural communities of Ottawa. This draw is based on the novelty of indoor wave swims of the type produced at this facility.

 

 

CONSULTATION

 

The contents of this report have been shared with staff from many internal departments and divisions, including Legal Services; Financial Services; Parks & Recreation; Corporate Communications (Media Relations) and Supply. In addition, the Parks & Recreation branch has brought this matter and the recommendations contained herein to the attention of Council’s Parks and Recreation Advisory Committee. The Committee has endorsed these recommendations. The concerns of the Ward 11 and Ward 2 councillors were considered in developing the recommendations in this report.

 

 

SUPPORTING DOCUMENTATION

 

Document 1 – Splash Wave Pool Floating Bulkhead Configuration

 

 

DISPOSITION

 

Subject to approval of this report, RPAM will proceed with the completion of design for the permanent dividing wall and will issue a tender for its construction.


Document 1